The recommendation package for the Whistling Ridge wind power project in southeastern Skamania County is now being considered by the office of Gov. Christine Gregoire.

The state Energy Facility Site Evaluation Committee (EFSEC) transmitted its proposal, including a draft Site Certification Agreement for the proposed wind farm, to the Governor on Jan. 5. That started the clock ticking on the Governor's review, which could take up to 60 days. The Governor's options are to approve the proposal as recommended, deny it or send it back to EFSEC with instructions for reconsideration.