I-84 blast causes long delay Monday

CREW cleans up crushed containers and other debris after Monday’s blast.

Rocks, and rolling slowdown, will echo at least three more times on Interstate 84 this month.

Monday saw the longest delay yet in the blasting project seven miles west of Hood River, the fourth of a total of seven planned freeway closures as Oregon Department of Transportation extends the latest segment of the Historic Columbia River Highway State Trail. Between 1-2 p.m. Monday, east-bound traffic was backed up to Cascade Locks, nine miles west.