Fear of a blowout has been reduced, but Grant County Public Utility District officials are still puzzling over what to do about a worrisome 2-inch, 65-foot long horizontal crack discovered late last month along one of the 12 spillways at central Washington’s Wanapum Dam on the Columbia River.

The damage was first discovered on Feb. 24 by a dam worker who noticed a section of the spillway deck had shifted slightly. Utility engineers then examined the area and found that one of the spillway pier monoliths had moved 2 inches out of alignment.