THE DALLES — Consor Engineering (CE) consultants Austin Rambin and Deb Galardi presented an updated financial analysis of The Dalles’ wastewater facility master plan at the Nov. 9 city council meeting, forecasting $92 million in costs over a 10-year window, adjusted for inflation.
The drafted plan, a 20-year capital improvement program, is under review by the city and the Department of Environmental Quality (DEQ) and will return to council for adoption in December.
During the presentation, CE focused on the first 10 years, with the ultimate goals of “determining what overall revenue increases are needed to meet the capital and ongoing operating needs” and “setting equitable and defensible rates based on the costs of serving customers,” Galardi said.
Financial projections indicate that the first 10 years will cost roughly $75 million in capital projects — about $41 million in years one through five and $32 million over the next five. With inflation and operating costs included, however, the forecast leaps to $92 million.
Major near-term projects include secondary-treatment upgrades to meet a new ammonia limit and rehabilitation of the Columbia River outfall, both required by DEQ.
CE said continuing annual rate increases at 3% would generate only about $15 million in capital funding over the projection period, short of the identified needs. Their preliminary model indicated increases of about 6.5% annually, assuming moderate customer growth and that roughly 70% of capital costs could be financed through the Oregon Clean Water State Revolving Fund (SRF).
They characterized the estimate as a starting point; the city plans to assess alternative financing options, including a federal credit program called the Water Infrastructure Finance and Innovation Act (WIFIA).
CE also recommended adjusting wastewater charges to better align them with the costs of serving certain customers. The proposal included a $5.77 monthly change per equivalent residential unit for authorized and permitted industrial users; a per-site charge for customers requiring fats, oils, and grease services; and higher strength surcharges.
The proposed realignment would make the first-year base-rate increase about 4.7% rather than 6.5%, with 6.5% increases in subsequent years in the model.
Councilors questioned how state and federal loans or grants, including SRF and WIFIA, might affect rates and debt, and how potential future tax revenues could factor into long-range planning. CE said the projection already assumed SRF-type financing, while other funding and revenue sources should be pursued but not relied on prematurely.
After it’s approved by the DEQ, the plan will return for council’s adoption on Dec. 14.