After several night closures this week to replace the lift span motors, the Port of Hood River prepares for even more maintenance work, and subsequent bridge closures, in the near future.

The first phase of on-site work, which involved lifting and attaching skew wiring, was performed by Hage Electric on April 3-4. The bridge was then completely closed the nights of April 9-10 to lift the bridge so workers could physically replace the lift span motors, and the bridge will be closed again the nights of April 17 and April 29 to recommission the bridge and remove equipment. Motorists should also expect intermittent lane closures and delays April 25-26.