Beginning 7 a.m. Monday, Jan. 27, E. Scenic Drive will be closed for for approximately 14 days as Crestline Construction begins work on the E. Scenic Drive Stabilization, Phase 2 Project for the City of The Dalles.

Work will take place on E. Scenic Drive approximately 300 feet east of Jefferson Street, between E. 16th Street and Jefferson Street. Work days will be Monday-Friday, 7 a.m. to 5 p.m., but the road will remain closed for the duration of the project (Feb. 12).