Featured
  • Updated

They don’t mess with the master.

The master schedule for constructing the new Holiday Inn Express on West Sixth, that is.

Robert Wymore, with the general contractor Integrity Structures, said they are on schedule to gain occupancy by the beginning of the year.

Now listen to this. That’s four stories, 54,000 square feet, start to finish in sixth months. That’s, to quote Jimmy John, freaky fast.

Wymore is quick to point out that it has taken a remarkable team thus far. Integrity has had 64 workers on site some days, putting in 640 hours a day.

  • Updated

Framing is moving along quickly at the Holiday Inn Express Construction site on West Sixth next to Franz Bakery.